PERT Estimate Calculator Widget

Embed a PERT three-point estimator for project planning. Readers list up to six tasks with optimistic, most likely and pessimistic estimates and get the expected duration and spread of each, plus a total with ranges they can put into a plan.

Business & Ecommerce Calculator Runs in your browser Free · no ads

Customize your widget

Theme
Auto follows the visitor's light/dark setting.
Style
Attribution on your page
Optional and entirely your choice. The exact line is shown in the code below; it links to the tool with rel="nofollow".
More options
Starting values
Leave blank to use the widget's defaults. Visitors can still change every value.

Live preview

Exactly what your visitors will see

Embed code

<iframe src="https://a2z.tools/embed/w/pert-estimate-calculator" title="PERT Estimate Calculator by A2Z Tools" width="100%" height="700" style="border:0;width:100%" loading="lazy" allow="clipboard-write"></iframe>

A plain iframe. Works everywhere, including site builders that strip scripts. Adjust height if your content needs more room.

Works with

How it works

The Program Evaluation and Review Technique was developed for the US Navy's Polaris programme and published by Malcolm, Roseboom, Clark and Fazar in 1959. Each task gets three estimates: optimistic (O), most likely (M) and pessimistic (P). The expected time weights the most likely value four times, (O + 4M + P) / 6, and the standard deviation is a sixth of the range, (P - O) / 6. A design task of 2, 4 and 8 days has an expected 4.33 days and a deviation of 1 day. For tasks done one after another the means add up, but the deviations do not: the variances (squared deviations) add, and the total deviation is their square root. Design plus a 3/5/13 build task gives 10.33 days with a deviation of 1.94, so about 68% of outcomes fall within one deviation (8.39 to 12.28) and about 95% within two (6.45 to 14.22).

Calculation method

  • Expected time per task = (O + 4M + P) / 6
  • Standard deviation per task = (P - O) / 6; variance = sd squared
  • Total mean = sum of means; total sd = sqrt(sum of variances)
  • ~68% range = mean +/- 1 sd; ~95% range = mean +/- 2 sd (normal approximation)

Worked examples

Two tasks in sequence

Inputs: Design, 2, 4, 8 and Build, 3, 5, 13 (days)

Result: Expected 10.33 days; sd 1.94; ~68% range 8.39 - 12.28; ~95% range 6.45 - 14.22

Means 4.33 + 6; variances 1 + 2.78.

Three-task default

Inputs: Design 2/4/8, Build 3/5/13, Testing 1/2/4

Result: Expected 12.5 days; sd 2.01; ~95% range 8.49 - 16.51

Testing adds 2.17 days and 0.25 to the variance.

Limitations

  • Assumes tasks run one after another and are independent; shared risks make the real spread wider.
  • The beta-distribution shortcut and the normal approximation are rough for one or two very skewed tasks.
  • Up to six tasks, typed as text lines.

Where publishers use it

  • Project-management blogs and PMP exam-prep sites teaching three-point estimating
  • Software teams estimating a feature from design to release
  • Construction and event planners sizing a schedule with uncertain steps
  • Agency proposal pages showing a delivery range rather than one date
  • University operations-research and engineering-management course pages
  • Research labs and grant applicants estimating experiment and fieldwork phases

Questions

Why weight the most likely estimate by four?

The original PERT method approximates each task with a beta distribution; (O + 4M + P) / 6 is the mean of that approximation. For 2, 4 and 8 days it gives 4.33 rather than the simple average of 4.67.

Why not just add the standard deviations?

Independent uncertainties partly cancel out. Two tasks with deviations of 1 and 1.67 days combine to sqrt(1 + 2.78) = 1.94, not 2.67.

How should I enter the tasks?

One task per line as name, optimistic, most likely, pessimistic - for example Build, 3, 5, 13. The name is optional; the three numbers must be in order O <= M <= P.

What does the 95% range mean?

If the estimates are honest and the tasks independent, about 95 times in 100 the total should land within two deviations of the mean. With 10.33 +/- 3.89 days that is 6.45 to 14.22.

Does it find the critical path?

No. It assumes the tasks run in sequence. For parallel work, run it separately for the longest chain of dependent tasks.

Sources

  1. Application of a Technique for Research and Development Program Evaluation (Operations Research 7(5): 646-669, 1959) - D. G. Malcolm, J. H. Roseboom, C. E. Clark, W. Fazar - INFORMS; record on RePEc IDEAS . The original PERT paper: activity time estimates from responsible technical people, expressed in probability terms; source of the three-estimate mean and spread used here. Publisher page (doi 10.1287/opre.7.5.646) blocked automated access on 2026-10-01; abstract checked on RePEc.

Cite or recommend this tool

If you reference this tool in an article, course or documentation, these formats are ready to copy. They are optional - nothing is added to your site unless you paste it.

A2Z Tools PERT Estimate Calculator
https://a2z.tools/pert-project-estimator
  • Project Profit Calculator

    Business & Ecommerce Calculator New

    Profit, margin, effective hourly rate and budget burn for a fixed-fee or hourly client project.

    Get code
  • Statistics Calculator

    Education & Math Calculator

    Mean, median, mode, range, variance, standard deviation and quartiles of any list of numbers.

    Get code
  • Business Days Calculator

    Time & Date Calculator

    Count working days between dates or add N business days, with your weekend and holidays.

    Get code
  • Profit Margin Calculator

    Business & Ecommerce Calculator

    Profit, gross margin and markup from cost and price - or the price for a target margin.

    Get code
  • Markup Calculator

    Business & Ecommerce Calculator

    Selling price from cost plus markup, or work back to the cost or the markup you applied.

    Get code
  • Discount Calculator

    Business & Ecommerce Calculator

    Sale price and savings, including stacked discounts and sales tax on the reduced price.

    Get code

Preview